Frews Contracting Ltd

Frews Contracting Ltd have applied to change conditions to alter the requirement to meet certain contaminant limits.

Current status: The decision of the Hearing Commissioner to grant the application with conditions has been released (PDF file, 3MB).

Notified proposal

We have received an application from Frews Contracting Limited for a change in conditions to their existing discharge permit CRC201182, to alter the requirement to meet certain contaminant limits as set out in ‘Schedule CRC201182B Managed Fill Waste Acceptance Criteria (MFWAC) and Cover Soil Quality’.

Consent process timeline

Application lodged

Notification and submission period

Hearing

Decision

This application is being sought to change conditions of CRC201182 which authorises the discharge of contaminants to land from a managed fill facility at Plantation Road, Hororata, legally described as Lot 1 DP459187, Lot 2 DP459187 and RS28998 and and located at or about, map reference NZTM 2000 1516580mE, 5180658mN.

Frews Contracting Limited proposes to:

  • Cancel part of Schedule CRC201182B, that sets MFWAC and Cover Soil Quality (CSQ) limits and rolling means for concentrations of; aluminium (Al), antimony (Sb), barium (Ba), manganese (Mn), and selenium (Se); and
  • Change part of Schedule CRC201182B, that sets CSQ limits and rolling means for concentrations of; organic compounds, chromium (Cr), and mercury (Hg).
    The existing discharge permit (CRC201182) is set to expire on 07 September 2042, no change to this consent duration is proposed.