Return to key areas of work

Organisational overview

Last updated: 20 November 2026
Reporting frequency: Quarterly

Our Annual Plan describes 34 service measures, each of which has one or more specific targets. In response to advice from Audit NZ in late 2025, we have added two further measures for River and Flood Resilience (19B and 19C) and we are now also reporting on those, making a total of 36 service measures. 

How did we do for the period 1 July to 30 September 2026?

We report on 36 service measures, each of which has one or more specific targets. Most targets are for the full year, so at the end of quarter one we report whether each measure is on track to be achieved by 30 June 2027. 

Context 

Severe flooding in July led to local states of emergency in Kaikōura and Waitaki, and resources were redirected to the response and recovery. 

Several new laws were also introduced in September: 

  • Planning Act 2026 and Natural Environment Act 2026 – these begin the move to a new resource management system. 
  • Emergency Management Act 2026 – this changes emergency management governance and roles, including the Emergency Management Committee. 
  • Local Government (System Improvements) Amendment Act 2026 – this focuses councils on cost-effective infrastructure, public services and regulatory functions, and strengthens performance reporting and accountability requirements. 

In early August, territorial authorities submitted proposals under the Government's Simplifying Local Government 'Head Start' process. Government decisions are now expected in early 2027.

Service performance

At the end of quarter one, 29 of 36 service measures are on track. Four measures will only have data later in the year, and one is not being measured this year. One measure is at risk and one will not be achieved: 

  • Service Measure 1 – Will not achieve. The review of the Regional Coastal Environment Plan cannot go ahead this year because of 'Plan Stop' provisions in resource management legislation, which paused councils' work on RMA plans. 
  • Service Measure 31 – At risk. There were 3.9 safety-related incidents per 100,000 passenger trips in quarter one, above the target of three or fewer. A review found that some operator incident reporting was incomplete in previous periods, so this result is not directly comparable with earlier results. 

Financial performance 

Combined expenditure across the three core services was $83.5 million for the quarter, $0.9 million (1.1%) above budget. Revenue was $1.5 million (1.7%) below budget. 

By core service, expenditure was $2.3 million (17.6%) above budget for Community Preparedness and Response to Hazards, $0.4 million (1.1%) above budget for Public Transport, and $1.8 million (6.1%) below budget for Environmental Regulation and Protection. Material items at an individual service level creating variances to budget were: 

  • $2.4 million (Flood and River Resilience) increase in expenditure (25.3% above budget), mainly because of the response to and recovery from the July Kaikōura flooding, including urgent flood repair and restoration work. 
  • $0.9 million (Total Mobility) increase in expenditure (30% above budget), because demand was higher than budgeted. An additional $0.58 million from NZ Transport Agency Waka Kotahi (NZTA) partly offset this. 
  • $2.5 million (RMA consenting) reduction in revenue (36% below budget), because fewer applications were lodged and chargeable hours fell by about 30%. The cost-recovery target is therefore unlikely to be met, which means a greater share of consenting costs will be funded from general rates. 
  • $12.7 million (Pest Management) in additional central government funding received for the Canterbury Wilding Conifer Control Programme, which was not in the budget. 

Key points for quarter one:

The highlights across the three core services in quarter one were:

  • Flood protection repairs were completed at 15 priority sites on the Kowhai River following the July flooding in Kaikōura, and the Council approved $5.09 million for the next phase of recovery work. 
  • All 12 Regional Infrastructure Fund projects are on track. The programme is upgrading stopbanks, floodgates and flood warning systems across the region. 
  • 95.6% of resource consent decisions were made within statutory timeframes, exceeding the 95% target and up from 83.6% in 2025/26. 
  • Plan Change 8 was notified on 4 July 2026 and received 110 submissions. It aims to give water users more flexibility and certainty while keeping environmental safeguards. 
  • About 3.97 million passenger trips were made on public transport, 3.7% more than in quarter one 2025/26. 
  • Concession fares moved to contactless payment and Motu Move cards on 23 September, making it simpler to pay for travel. More than two million trips have now been paid for through Motu Move since it was introduced. 
  • Metro took over the Rolleston–Christchurch direct service trial, and the Route 110 trial began between New Brighton and The Palms via Aranui. 
  • Three community funds totalling $1.2 million opened for applications in September, supporting community-led environmental projects across the region. 
  • A cross-organisational work programme is underway to prepare for the potential impacts of El Niño, focused on awareness and engagement, monitoring and intelligence, and operational and regulatory readiness. 
  • We have set up a cross-organisational team to prepare, with national agencies and regional partners, for a response if Highly Pathogenic Avian Influenza (HPAI, or bird flu) is detected in Waitaha Canterbury. 

Core Services Performance Report | Pūrongo Ratonga Matua

The Pūrongo Ratonga Matua Core Services Performance Report for the period 1 July – 30 September 2026 (quarter one) was received by the Council's Regional Delivery Committee at its meeting on 18 November 2026.   

 Download the Core Services Performance Report | Pūrongo Ratonga Matua for quarter one 2026/27 (PDF, 2.09MB)

Financial performance

1 July to 30 September 2026
RevenueExpenditureSurplus
Actual$85.68M$83.49M$2.19M
Budget$87.19M$82.57M$4.62M
Variance-$1.50$0.92-$2.43
% Variance-1.73%1.12%

The Council ended quarter one with a surplus of $2.19 million, $2.43 million less than the budgeted surplus of $4.62 million for the quarter. Combined expenditure across the three core services was $0.9 million (1.1%) above the quarter one budget set in the Annual Plan 2026/27.

Expenditure

The Council ended quarter one with a surplus of $2.19 million, $2.43 million less than the budgeted surplus of $4.62 million for the quarter. Combined expenditure across the three core services was $0.9 million (1.1%) above the quarter one budget set in the Annual Plan 2026/27. Any surplus at the end of the financial year will be used to replenish reserves unless directed otherwise by Council. 

Return to key areas of work Top